  • Advisory Note: Extension of Time
21 Apr
  • ♥302 Likes

JBCC  A/N 2023  : ADMINISTERING EXTENSION OF TIME FOR PRACTICAL COMPLETION

 

Delays where the contractor is not at fault would normally constitute a valid claim for extension of time (EOT). If the delay affects the critical path of the project, it would normally result in the revision of the contractual completion date of the project. However, confirming a delay and/or disruption is not an easy task; and furthermore, it is a time-consuming process, especially in multifaceted projects with thousands of activities, a lot of details, as well as the involvement of many stakeholders.

 

read the full article here.

« Advisory Note: LoadsheddingAdvisory Note: Adjudication as Alternative Dispute Resolution Process »
logo
Providing the building industry with a series of contract administration tools of choice suitable for a variety of applications in English speaking countries since 1997.

Get in Touch

  • reception@jbcc.co.za
  • 011 482 3102
  • Coachman’s Crossing Office Park, Block A Unit 1, 4 Brian Street, Bryanston
  • 09:00 am - 04:00 pm

Latest News

ASAQS: Future-Proofing the Quantity Surveying Profession

May 2, 2025

Welcoming Gerhard de Leeuw as JBCC Board Member

April 7, 2025
© JBCC 2022     |    Proudly created by Cassandra Kidson & Associates