JBCC N/S SUBCONTRACT AGREEMENT: CLAIMING FOR DELAYS CAUSED BY COVID 19
PANDEMIC
There is an officially declared international pandemic. There have been consequences to contractors and subcontractors resulting from this pandemic. These consequences will probably continue and manifest in different ways at different times. In addition to local effects, for subcontractors that import goods or services, the effects of the pandemic on the source countries is not part of the local experience and great care must be taken to raise and give notice of a potential delay when such a possibility becomes known to the subcontractor. Each specific event or circumstance must be recorded in a notice, rights reserved and thereafter any actual delay claimed in a claim for the revision of the date of interim completion.