JBCC N/S SUBCONTRACT AGREEMENT:
CLAIMING FOR DELAYS CAUSED BY COVID 19

PANDEMIC 

There is an officially declared international pandemic. There have been consequences to contractors and
subcontractors resulting from this pandemic. These consequences will probably continue and manifest in different
ways at different times. In addition to local effects, for subcontractors that import goods or services, the effects of
the pandemic on the source countries is not part of the local experience and great care must be taken to raise and
give notice of a potential delay when such a possibility becomes known to the subcontractor.
Each specific event or circumstance must be recorded in a notice, rights reserved and thereafter any actual delay
claimed in a claim for the revision of the date of interim completion.

 

read the full article here.

« The rising demand for qualified adjudicators25th Anniversary Gala Dinner »
logo
Providing the building industry with a series of contract administration tools of choice suitable for a variety of applications in English speaking countries since 1997.

Get in Touch

  • reception@jbcc.co.za
  • 011 482 3102
  • Coachman’s Crossing Office Park, Block A Unit 1, 4 Brian Street, Bryanston
  • 09:00 am - 04:00 pm

Latest News

ASAQS: Future-Proofing the Quantity Surveying Profession

May 2, 2025

Welcoming Gerhard de Leeuw as JBCC Board Member

April 7, 2025
© JBCC 2022     |    Proudly created by Cassandra Kidson & Associates