The Concept of ‘works completion’ was introduced in the 2005 and 2007 editions of JBCC® PBA and NSSA agreements – after practical completion (occupation by the employer) to allow the contractor to complete outstanding items within 20 working days, or forfeit compensatory interest … etc, the only ‘punishment’ for non compliance

* Not successful – discontinued in the 2014 Edition of JBCC® agreements

See: 5.0P-25.0; 5.0N-25.0; 4.1P-25.0; 4.2N-25.0