Is an essential administration tool but not a contract document.

The principal agent may point out to the contractor that without a programme the “revision of the date for practical completion” clause can not be applied and hence the contractor is at risk that penalties will be imposed from the contractual date for practical completion until the actual date of practical completion.

The principal agent may not interfere with the contractor’s programme

Revisions to the programme must be identified when the date for practical completion is revised

See: 6.1P-12.2.6 and 23.5; 5.0P-15.6 and 29.6