Described in the PBA: The contractor shall pay all subcontractors within seven (7) calendar days of the due date for payment by the employer [CD];

Described in the NSSA: The contractor shall pay the subcontractor the amount certified in an issued n/s subcontract payment advice within twenty one (21) calendar days of the date for issue of the Payment Certificate including default interest [NSSA-CD]

See: 6.1P-25.11; 6.1N-25.7