The principal agent will have to review the entire original (or approved revised) programme = and compare it to actual progress compared – referenced to the critical path and the date for practical completion; this should result in a number of (working) days extension (to be) granted = revised date for practical completion

Any subsequent claims for revision of the date for practical completion must be processed in the same manner

Where the JBCC® MWA is used the details of the revised date for practical completion must be recorded in the contract minutes, no other correspondence is required

See: 5.1M-17.0; 4.0M-11.0; 3.1M-11.0