Traditionally defined as a month holiday over the Christmas period – currently applicable in some provinces only. At tender stage the contractor must complete in the Contract Data the anticipated holiday periods during the construction period of a project to allow the principal agent to fairly assess possible extension of time claims later

See: 6.1P[CD]-19/20/24; 6.1N[CD]-19/20/24; 5.1M[CD]-15/17/18